Anticipated dates for Wiltshire Council’s surface dressing programme

Below are the anticipated dates (dependent on weather conditions) and links to One.Network for our Surface Dressing Programme from Wiltshire Council.

C76 (Part), Crudwell; 28 – 30 April 2026 https://one.network/?tm=GB147871701

C92 (Part), Crudwell and Hankerton; 28 – 30 April 2026 https://one.network/?tm=GB147871253

Temporary Closure of: C92 (Part), Hankerton (27.04.2026)

https://api-gb.one.network/downloads/tm/1142/notice-2_4127e96f2b.pdf

https://api-gb.one.network/downloads/tm/1142/indicative-plan_148822951_4095165_c9c0367210.pdf

Please see the above links to the Notice and Indicative Plan for a Temporary Traffic Regulation Order (TTRO) for C92 (Part), Hankerton commencing 27th April 2026.

To enable: WESSEX WATER SERVICES LIMITED to carry out water main replacement scheme and other associated works.

The closure can also be found on one.network here:  https://one.network/?tm=GB148822951

Temporary Closure of: C85 (Part), Oaksey (13.04.2026)

https://api-gb.one.network/downloads/tm/1142/recommencement-notice_58be031fc4.pdf

https://api-gb.one.network/downloads/tm/1142/indicative-plan_147491519_4064877_bca5d39507.pdf

Please see the above links to the Notice and Indicative Plan for a Temporary Traffic Regulation Order (TTRO) for C85 (Part), Oaksey commencing 13th April 2026.

To enable: Wessex Water to carry out sewer repair work and other associated works.

The closure can also be found on one.network here:  https://one.network/?tm=GB147491519

Temporary Closure of: C92 (Part), Hankerton (20.04.2026)

https://api-gb.one.network/downloads/tm/1142/notice-2_0c9410e18c.pdf

https://api-gb.one.network/downloads/tm/1142/indicative-plan_148374813_4083530_2752c37271.pdf

Please see the above links to the Notice and Indicative Plan for a Temporary Traffic Regulation Order (TTRO) for C92 (Part), Hankerton commencing 20th April 2026.

To enable: OPENREACH LIMITED to carry out ducting works, pole installation works and other associated works.

The closure can also be found on one.network here:  https://one.network/?tm=GB148374813

Urgent closure of Flisteridge Road, Minety – 18/02/26

https://api-gb.one.network/downloads/tm/1142/flisteridge-road-minety_148502858_4083415_c4228b77f4.pdf

Please see the above link to an urgent closure notice for Flisteridge Road, Minety commencing 18th February 2026.

To enable: Openreach to carry out urgent pole repair/ service restoration works and other associated works.

The closure can also be found on one.network here:  https://one.network/?tm=GB148502858

Roadworks – Crudwell to Eastcourt rescheduled to start on 4th February 2026

Road Carriageway Works – C76 – C76 CRUDWELL TO EASTCOURT

The carriageway repair works programmed on C76 – C76 CRUDWELL TO EASTCOURT in December were postponed due to bad weather.

These works involve asphalt patch repairs, adjustment of ironwork, reinstatement of road markings and associated maintenance works.

The works will now commence on Wednesday the 4th of February 2026 and will be completed by Sunday the 8th of February 2026 between the hours of 09:30 and 15:00, however on occasions they may over run due to uncontrollable circumstances such as plant breakdowns, if weather conditions are unfavourable, or occasionally we discover the need for additional repairs once the work has started.

Should you require any further information in advance of the works please refer to (https://one.network/?tmi=GB43138314).

Temporary Road Closure at Eastcourt commencing 4 March 2026

Details of forthcoming road closure at Eastcourt – to enable: Openreach to carry out pole installation works and other associated works.

https://api-gb.one.network/downloads/tm/1142/notice-2_ab3fef3240.pdf
https://api-gb.one.network/downloads/tm/1142/indicative-plan_147495702_4055752_e8d115609d.pdf

Please see the above links to the Notice and Indicative Plan for a Temporary Traffic Regulation Order (TTRO) for C76 (Part) and C83 (Part), Crudwell commencing 4th March 2026.

The closure can also be found on one.network here:  https://one.network/?tm=GB147495702

Update on 9 January 2026: in addition, please see the above links to the Notice and Indicative Plan for a Temporary Traffic Regulation Order (TTRO) for C83 (Part), Oaksey commencing 9th March 2026.

To enable: Openreach to carry out works to install new poles and other associated works.

https://api-gb.one.network/downloads/tm/1142/notice-2_26c6e199af.pdf

https://api-gb.one.network/downloads/tm/1142/indicative-plan_147321958_4057682_ad12abae3b.pdf

The closure can also be found on one.network here:  https://one.network/?tm=GB147321958

Road Carriageway Works –  C92 – Murcott

Road Carriageway Works – C92 – Murcott

Carriageway repair works programmed on C92 – Murcott.

The site extents can be viewed on the attached drawing: 117941-ATR-HSN-2627SD_0417-DR-CH-000001_C01

These works involve asphalt patch repairs, adjustment of ironwork, reinstatement of road markings and associated maintenance works.

The works will commence on Monday the 3rd of November 2025 and will be completed by Thursday the 6th of November 2025 between the hours of 07:00 and 19:00, however on occasions they may over run due to uncontrollable circumstances such as plant breakdowns, if weather conditions are unfavourable, or occasionally we discover the need for additional repairs once the work has started.

There will be advance information signs erected on site giving confirmed start dates.

Road Markings and Ironwork adjustments may need to be completed at a later date.

The main diversion route for all ‘through’ traffic whilst works are being undertaken within the road closure will be as per the attached road diversion drawing.

The Contractor will maintain pedestrian access for residents for the duration of the works; but depending upon what operation is being undertaken and where it’s being undertaken residents may find that when accessing or egressing from their property in their vehicle, they may experience a delay and have to wait for plant to be moved out of the carriageway. I have suggested to residents that when leaving their property, to allow extra time for any possible delays and when returning to their property, there will be traffic management operatives located at the extents of the works, to speak to them, explain where they live, and they will be able to assist.

There will be points during the material laying process where vehicular access will be restricted as residents won’t be able to drive over the newly laid material, as early trafficking could lead to premature failure, therefore I have recommended to residents that if works are being undertaken in the vicinity of their property to speak to the workforce in advance to ask if there will be any restrictions with regards to access.

Advanced signing will be erected and letter drops to all residents located within the site extents will commence week starting 20th of October 2025. Signing will be in place advising that local businesses will be open as usual.